Last updated: 14 May 2024
Roadworks | Location | Suburb/area | Treatment/impact on users | Start date | Expected end date |
Road Reconstruction | Ahuroa Road (full road closure, Wenzlick Road to Ahuroa Road) | Ahuroa/Puhoi | Continuous Deployment | 25/03/2024 | 30/09/2024 |
Digout | Lonely Track Road | Albany Heights | Stop/ Go | 16/05/2024 | 16/05/2024 |
Minor Safety Project | Ararimu Road | Ararimu | Stop/Go - Try alternate route | 16/04/2024 | 17/05/2024 |
Road Reconstruction | Albert Street (full road closure, 85 Albert Street to 135 Albert Street) | Auckland Central | Continuous Deployment | 30/06/2021 | 30/06/2024 |
Crane Operation | Albert Street (full road closure, Albert Street/Mill Lane/Wolf Street intersection to Wyndham Street) | Auckland Central | Continuous Deployment | 10/05/2024 | 13/05/2024 |
Road Reconstruction | BeresFord Square (full road closure, 22 Beresford Square to 6 Beresford Square) | Auckland Central | Continuous Deployment | 29/06/2023 | 30/06/2024 |
Road Reconstruction - Structural Repairs | Customs, Sturdee Street (to Albert Street) | Auckland Central | Day - Lane Closure - Capacity reduced | 29/04/2024 | 31/07/2024 |
Repairs to Structure | Emily Place (full road closure, 5 Emily Place to 21 Emily Place) | Auckland Central | Day Shift Only | 20/05/2024 | 24/05/2024 |
Repairs to Structure | Gore Street Lane (full road closure, Gore Street to Fort Street) | Auckland Central | Day Shift Only | 21/05/2024 | 23/05/2024 |
Telecommunications Installation | Kitchener Street (full road closure, Courthouse Ln to Bacons Ln) | Auckland Central | Night Shift Only | 13/05/2024 | 16/05/2024 |
Road Reconstruction | Mayoral Drive (full road closure, Wellesley Street W to 15 Mayoral Drive) | Auckland Central | Continuous Deployment | 30/06/2021 | 30/06/2024 |
Electrical Installation | Mercury Lane (full road closure, Cross Street to Canada Street) | Auckland Central | Continuous Deployment | 15/05/2024 | 31/05/2024 |
Electrical Installation | Mercury Lane (full road closure, K Road to Cross Street) | Auckland Central | Continuous Deployment | 13/05/2024 | 22/06/2024 |
Road Reconstruction | Victoria Street West (full road closure, 75B Victoria Street W to 20 Victoria Street West) | Auckland Central | Continuous Deployment | 30/06/2021 | 30/06/2024 |
Jungle Concert | Mahuhu Crescent (full road closure, Tapora Street to Beach Road ) | Auckland Central | Full road closured for the Jungle Concert from 8.30pm to 1am | 15/05/2024 | 16/05/2024 |
Jungle Concert | Mahuhu Crescent (full road closure, Tapora Street to Te Tatou Crescent ) | Auckland Central | Full road closured for the Jungle Concert from 5pm to 1am | 15/05/2024 | 16/05/2024 |
Jungle Concert | Tangihua Street (full road closure, Full Length of Road) | Auckland Central | Full road closured for the Jungle Concert from 9.30pm to Midnight | 15/05/2024 | 16/05/2024 |
Jungle Concert | Tapora Street (full road closure, Full Length of Road) | Auckland Central | Full road closured for the Jungle Concert from 8.30pm to 1am | 15/05/2024 | 16/05/2024 |
Jungle Concert | Te Taou Crescent (full road closure, Full Length of Road) | Auckland Central | Full road closured for the Jungle Concert from 8.30pm to 1am | 15/05/2024 | 16/05/2024 |
Minor Safety Project | Awhitu Road | Awhitu | Stop/Go - Try alternate route | 6/05/2024 | 18/07/2024 |
PCC Kemp Road Hill Climb | Kemp Road (full road closure, Full Length of Road) | Awhitu | Full road closured for the PCC Kemp Road Hill Climb from 10am to 4pm | 26/05/2024 | 26/05/2024 |
AC Reseal | Merrill Place | Birkenhead | Stop/ Go | 16/05/2024 | 16/05/2024 |
Asphalt Reseal | Brookby Road | Brookby | Road Closure | 5/05/2024 | 23/05/2024 |
Choose Reason from Dropdown | Masterton Road (full road closure, 48A Masterton Road to 54 Masterton Road) | Browns Bay | Continuous Deployment | 6/05/2024 | 5/06/2024 |
Digout | Clevedon Kawakawa Road | Clevedon | Stop/Go - Try alternate route | 15/05/2024 | 20/05/2024 |
Guard Rail | Papakura Clevedon Road | Clevedon | Stop/Go - Try alternate route | 15/05/2024 | 15/05/2024 |
Culvert Renewal | Dairy Flat Highway (between Durey Road and Potter Road) | Dairy Flat | Stop/Go - Day Shift Only | 1/05/2024 | 17/05/2024 |
AC Reseal | Ngataringa Road | Devonport | Stop/ Go | 14/05/2024 | 14/05/2024 |
Stormwater Improvement | Queens Parade (full road closure, Victoria Road to Wynyard Street) | Devonport | Continuous Deployment | 6/05/2024 | 19/05/2024 |
Road Reconstruction | Quarry Road (full road closure, Harrison Road to Maketu Road) | Drury | Continuous Deployment | 6/05/2024 | 21/06/2024 |
Road Maintenance | Nikau Street (full road closure, 32 Nikau Street to Ruru Street) | Eden Terrace | Continuous Deployment | 2/04/2024 | 10/06/2024 |
Water Supply Improvement | Nikau Street (full road closure, Korari Street to Ruru Street) | Eden Terrace | Continuous Deployment | 22/04/2024 | 31/05/2024 |
Road Maintenance | Ruru Street (full road closure, 10 Ruru Street to Nikau Street) | Eden Terrace | Continuous Deployment | 2/04/2024 | 10/06/2024 |
Road Reconstruction - Footpath, Kerb & Channel | Saint Andrews Road (to Selwyn Road) | Epsom | Day - One Direction Detour - Stop/Go Control | 25/03/2024 | 15/06/2024 |
Footpath | Staverton Place | Favona | Lane closure. Stop/Go. Minor impact to traffic | 13/05/2024 | 17/05/2024 |
AC Reseal | Longwood Place | Forrest Hill | Stop/ Go | 13/05/2024 | 13/05/2024 |
Road Reconstruction - Footpath, Kerb & Channel | Barrie Street (to Picton Street) | Freemans Bay | Day - Lane Closure - Capacity reduced | 13/05/2024 | 8/06/2024 |
Road Resurfacing - Asphalt Reseal | Cascade Street (AT-W168751 to Runnell Street) | Freemans Bay | Night - Road Closure | 19/05/2024 | 20/05/2024 |
Road Resurfacing - Asphalt Reseal | College Hill (AT-W168751 to Wood Street) | Freemans Bay | Night - One Direction Detour - Stop/Go Control | 14/05/2024 | 20/05/2024 |
Road Resurfacing - Asphalt Reseal | Gudgen Street (AT-W168751 to Hargreaves Street) | Freemans Bay | Night - Road Closure | 13/05/2024 | 14/05/2024 |
Road Resurfacing - Asphalt Reseal | Hargreaves Street (AT-W168751 to Finish at West End) | Freemans Bay | Night - Road Closure | 12/05/2024 | 13/05/2024 |
Road Reconstruction - Footpath, Kerb & Channel | Smith Street (to Road End) | Freemans Bay | Day - Road Closure | 27/05/2024 | 11/06/2024 |
Road Reconstruction - Cycleway Project | Apirana Avenue (Apirana Avenue to Taniwha Street Roundabout) | Glen Innes | Day - One Direction Detour - Stop/Go Control | 23/11/2023 | 19/06/2024 |
Water Supply Improvement | Epping Street (full road closure, Harlow Crescent to Heatherbank Street) | Glen Innes | Continuous Deployment | 8/02/2024 | 30/05/2024 |
Road Reconstruction - Cycleway Project | Morrin Road (to Merton Road) | Glen Innes | Day - One Direction Detour | 15/04/2024 | 31/05/2024 |
Road Improvements | Archers Road (full road closure, 2A Archers Road to 112A Archers Road) | Glenfield | Night Shift Only | 5/05/2024 | 17/05/2024 |
Road Improvements | Archers Road (full road closure, 85 Archers Road to 177 Archers Road) | Glenfield | Night Shift Only | 5/05/2024 | 17/05/2024 |
Road Maintenance | Bentley Avenue (full road closure, 4A Bentley Avenue to Chartwell Avenue) | Glenfield | Night Shift Only | 12/05/2024 | 16/05/2024 |
Asphalt Reseal | Chartwell Avenue | Glenfield | One Way Detour | 13/05/2024 | 16/05/2024 |
Digout | Chartwell Avenue | Glenfield | Stop/ Go | 12/05/2024 | 13/05/2024 |
Road Maintenance | Chartwell Avenue (full road closure, 70A Chartwell Avenue to Archers Road) | Glenfield | Night Shift Only | 12/05/2024 | 16/05/2024 |
Digout | Glenfield Road | Glenfield | Stop/ Go | 13/05/2024 | 15/05/2024 |
Road Maintenance | Marlborough Avenue (full road closure, 84 Marlborough Avenue to Chartwell Avenue) | Glenfield | Night Shift Only | 12/05/2024 | 16/05/2024 |
Road Maintenance | Ramillies Place (full road closure, 2 Ramillies Place to Chartwell Avenue) | Glenfield | Night Shift Only | 12/05/2024 | 16/05/2024 |
Road Maintenance | Raymond Terrace (full road closure, Lydia Avenue to Cul-de-sac) | Glenfield | Day Shift Only | 22/04/2024 | 30/09/2024 |
Road Maintenance | Marewa Road (full road closure, Green Lane West to 15 Marewa Road) | Greenlane | Day Shift Only | 13/05/2024 | 17/05/2024 |
Road Reconstruction - Footpath, Kerb & Channel | Picton Street (to Hepburn Street) | Grey Lynn/Ponsonby | Day - One Direction Detour - Stop/Go Control | 18/03/2024 | 18/06/2024 |
Road Reconstruction - Footpath, Kerb & Channel | Tahuna Street (to Road End) | Grey Lynn/Ponsonby | Day - Road Closure | 2/04/2024 | 11/05/2024 |
Unsealed Road Upgrade | Inland Road (between Sheffield Road and Rautawhiri Road) | Helensville | Stop/Go - Day Shift Only | 29/04/2024 | 29/05/2024 |
Water Supply Improvement | Kathryn Avenue (full road closure, 11A Kathryn Avenue to Oakdale Road) | Hillsborough | Day Shift Only | 8/04/2024 | 2/06/2024 |
Road Maintenance | Hobbs Road (full road closure, Roberts Road to House no.3) | Hobbs Bay | Stop/Go TTM | 22/04/2024 | 21/06/2024 |
Repairs to Structure | Brigham Creek Road (full road closure, State Highway 16 to Joseph McDonald Drive) | Hobsonville | Night Shift Only | 5/05/2024 | 17/05/2024 |
Road Improvements | Matua Road (full road closure, McIndoe Road to State Highway 16) | Huapai | Continuous Deployment | 6/05/2024 | 14/10/2024 |
Metalling/Grading | Moumoukai Hill Road | Hunua | Stop/Go - Try alternate route | 26/04/2024 | 13/05/2024 |
Minor Safety Project | Sky High Road | Hunua | Road Closure | 6/05/2024 | 21/06/2024 |
Road Maintenance | Sky High Road (full road closure, Highridge Road to Mathis Road) | Hunua | Continuous Deployment | 6/05/2024 | 21/06/2024 |
Footpath Enabling | Ramsgate Terrace | Mairangi Bay | Stop/ Go | 12/05/2024 | 16/05/2024 |
Concrete Works | Maraetai Drive | Maraetai | Stop/Go - Try alternate route | 22/04/2024 | 21/06/2024 |
Bridge Repairs | Whitford Maraetai Road | Maraetai | Stop/Go - Try alternate route | 17/05/2024 | 21/05/2024 |
Slip Repair | Matakana Valley Road (between Pakiri Road and Govan Wilson Road) | Matakana | Stop/Go - 24 hours (traffic lights) | 29/04/2024 | 1/07/2024 |
Sealed Road Maintenance | Milford Road | Milford | Road Closure | 12/05/2024 | 13/05/2024 |
Stormwater Improvement | Glass Road (full road closure, 49 Glass Road to Dominion Road Extension) | Mount Roskill | Continuous Deployment | 17/05/2024 | 5/06/2024 |
Road Reconstruction - Footpath, Kerb & Channel | Kimber Hall (Kimber Hall to White Swan Road) | Mount Roskill | Day - One Direction Detour - Stop/Go Control | 19/02/2024 | 16/05/2024 |
Pipeline Installation | Marion Avenue (full road closure, 6 Marion Avenue to May Road) | Mount Roskill | Continuous Deployment | 22/04/2024 | 6/06/2024 |
Road Improvements | Molley Green Place (full road closure, Full Length of Olympus Street) | Mount Roskill | Continuous Deployment | 20/06/2023 | 30/07/2024 |
Road Maintenance | Richardson Road (full road closure, 617A Richardson Road to Glass Road) | Mount Roskill/Owairaka | Continuous Deployment | 24/05/2024 | 27/05/2024 |
Unsealed Road Upgrade | Constable Road (between Taiapa Road and End Of Road) | Muriwai | Stop/Go - Day Shift Only | 29/04/2024 | 29/05/2024 |
Metalling/Grading | Oyau Mountain Road | Ness Valley | Stop/Go - Try alternate route | 14/05/2024 | 31/05/2024 |
Level Crossing Improvement/Maintenance | Kingdon street (full road closure, Short Street to end of the cul-de-sac ) | Newmarket | Continuous Deployment | 24/05/2024 | 8/06/2024 |
Telecommunications Installation | Stable Lane (full road closure, 146 Stable Lane to 185 Stable Lane) | Newton | Night Shift Only | 13/05/2024 | 15/05/2024 |
Road Improvements | Vaughans Road (full road closure, 189 Vaughans Road) | Okura | Continuous Deployment | 28/09/2023 | 28/09/2025 |
Road Reconstruction - Footpath, Kerb & Channel | Alfred Street (to Church Street) | Onehunga | Day - One Direction Detour - Stop/Go Control | 5/03/2024 | 22/06/2024 |
Road Maintenance | Arthur Street (full road closure, Spring Street to Alfred Street) | Onehunga | Night Shift Only | 22/05/2024 | 24/05/2024 |
Road Maintenance | Jackson Street (full road closure, Symonds Street to Pleasant Street) | Onehunga | Day Shift Only | 18/05/2024 | 30/05/2024 |
Road Maintenance | Jackson Street (full road closure, Symonds Street to Pleasant Street) | Onehunga | Day Shift Only | 29/04/2024 | 15/05/2024 |
Road Reconstruction - Footpath, Kerb & Channel | Jackson Street (to Symonds Street) | Onehunga | Day - One Direction Detour - Stop/Go Control | 9/05/2024 | 31/05/2024 |
Road Maintenance | Victoria Street (full road closure, Grey Street to Church Street) | Onehunga | Night Shift Only | 22/05/2024 | 24/05/2024 |
Bridge Repairs | Ponga Road | Opaheke | Stop/Go - Try alternate route | 14/05/2024 | 16/05/2024 |
Road Maintenance | Centreway Road (full road closure, Riverside Road RAB to Hibiscus Coast Highway State Highway 31) | Orewa | Night Shift Only | 12/05/2024 | 14/05/2024 |
Footpath Work | Criterion Street (full road closure, Atkinson Avenue to Great South Road) | Ōtāhuhu | Continuous Deployment | 29/01/2024 | 31/05/2024 |
Footpath, Kerb & Channel | Rodney Street | Ōtāhuhu | Lane closure. Stop/Go. Minor impact to traffic | 13/05/2024 | 17/05/2024 |
Road Improvements | Alamein Terrace (full road closure, Hargest Terrace to 16 Alamein Terrace) | Owairaka | Continuous Deployment | 20/11/2023 | 31/08/2024 |
Water Supply Improvement | Denize Road (full road closure, 9 Denize Road to Farrell Avenue) | Owairaka | Continuous Deployment | 28/04/2024 | 26/05/2024 |
Water Supply Improvement | Farrell Avenue (full road closure, 52 Farrell Avenue to Parkinson Avenue) | Owairaka | Continuous Deployment | 28/04/2024 | 26/05/2024 |
Water Supply Improvement | Farrell Avenue (full road closure, 68 Farrell Avenue to Parkinson Avenue) | Owairaka | Day Shift Only | 30/04/2024 | 19/05/2024 |
Road Improvements | Hargest Terrace (full road closure, 12 Hargest Terrace to 19 Hargest Terrace) | Owairaka | Continuous Deployment | 20/11/2023 | 31/08/2024 |
Water Supply Improvement | Jessop Street (full road closure, 5 Jessop Street to Farrell Avenue) | Owairaka | Continuous Deployment | 28/04/2024 | 26/05/2024 |
Road Improvements | Olympus Street (full road closure, 27 Olympus Street to Murray Halberg Rugby Field) | Owairaka | Continuous Deployment | 20/11/2023 | 31/08/2024 |
Road Improvements | Oakleigh Avenue (full road closure, Spartan Road to 48 Oakleigh Avenue) | Pahurehure/Ardmore | Night Shift Only | 12/05/2024 | 17/05/2024 |
Road Improvements | Rawson Way (full road closure, 2 Rawson Way to Spartan Road) | Pahurehure/Ardmore | Night Shift Only | 12/05/2024 | 17/05/2024 |
Road Improvements | Spartan Road (full road closure, Great South Road to 50 Spartan Road) | Pahurehure/Ardmore | Night Shift Only | 12/05/2024 | 17/05/2024 |
Road Improvements | Westbrook Avenue (full road closure, Spartan Road to 10 Westbrook Avenue) | Pahurehure/Ardmore | Night Shift Only | 12/05/2024 | 17/05/2024 |
Construction Vehicle Access | Seven Oaks Drive (full road closure, Dale Crescent to End of Road) | Pakuranga | Continuous Deployment | 26/09/2022 | 30/12/2026 |
Footpath | Cargill Street | Papakura | Lane closure. Stop/Go. Minor impact to traffic | 13/05/2024 | 15/05/2024 |
Rehab | Great South Road | Papakura | Night Lane closure. Stop/Go. Minor impact to traffic | 14/05/2024 | 14/05/2024 |
Footpath | Rice Crescent | Papakura | Lane closure. Stop/Go. Minor impact to traffic | 13/05/2024 | 17/05/2024 |
Rehab | Settlement Road | Papakura | Night Lane closure. Stop/Go. Minor impact to traffic | 13/05/2024 | 13/05/2024 |
Repairs to Structure | Courtenay Crescent (full road closure, Winthrop Way to Winthrop Way) | Papatoetoe | Continuous Deployment | 12/04/2024 | 30/06/2024 |
Rehab, Digouts | Portage Road | Papatoetoe | Day / Night Lane closure. Stop/Go. Minor impact to traffic | 15/05/2024 | 19/05/2024 |
Repairs to Structure | Winthrop Way (full road closure, Henwood Road to Raglan Street) | Papatoetoe | Continuous Deployment | 12/04/2024 | 30/06/2024 |
AC Reseal | Ridge Road | Paremoremo | Stop/ Go | 17/05/2024 | 17/05/2024 |
Pipeline Installation | The Crescent (full road closure, Domain Drive to Kiosk Road) | Parnell | Continuous Deployment | 29/04/2024 | 25/05/2024 |
Minor Safety Project | Kingseat Road | Patumahoe | Road Closure | 4/03/2024 | 14/05/2024 |
Road Maintenance | Laing Road (full road closure, Bryant Road to Urquhart Road) | Patumahoe | Day Shift Only | 23/05/2024 | 24/05/2024 |
Road Maintenance | Kingseat Road (full road closure, Glenbrook Road to Pearson Road) | Patumahoe / Awhitu | Continuous Deployment | 4/03/2024 | 19/05/2024 |
Road Reconstruction | Glenesk Road (full road closure, 1 Glenesk Road to 29 Glenesk Road) | Piha | Continuous Deployment | 28/09/2023 | 31/07/2024 |
Pipeline Installation | Benghazi Road (full road closure, 26 Benghazi Road to Dunkirk Road) | Point England | Continuous Deployment | 1/10/2023 | 15/05/2024 |
Pipeline Installation | Dunkirk Road (full road closure, Alamein Road to 81 Dunkirk Road) | Point England | Continuous Deployment | 1/10/2023 | 15/05/2024 |
Pipeline Installation | Dunkirk Road (full road closure, Tangaroa Street to Alamein Road) | Point England | Day Shift Only | 10/05/2024 | 29/07/2024 |
Intersection Improvements | Pirangi Street (full road closure, Tangaroa Street to Taukiri Street) | Point England | Continuous Deployment | 8/01/2024 | 31/05/2024 |
Pipeline Installation | Riverside Avenue (full road closure, Tuakiri Street to Tangaroa Street) | Point England | Day Shift Only | 10/05/2024 | 29/07/2024 |
Pipeline Installation | Tangaroa Street (full road closure, 13 Tangaroa Street to Dunkirk Road) | Point England | Day Shift Only | 10/05/2024 | 29/07/2024 |
Pipeline Installation | Tangaroa Street (full road closure, Dunkirk Road to River Side Avenue) | Point England | Continuous Deployment | 1/10/2023 | 15/05/2024 |
Intersection Improvements | Tangaroa Street (full road closure, Tripoli Road to Riverside Avenue) | Point England | Continuous Deployment | 8/01/2024 | 31/05/2024 |
Pipeline Installation | Tobruk Road (full road closure, Derna Road to Dunkirk Road) | Point England | Day Shift Only | 10/05/2024 | 29/07/2024 |
Tree Trimming | Kelland Road | Pollok | Stop/Go - Try alternate route | 15/05/2024 | 15/05/2024 |
Road Maintenance | Gudgeon Street (full road closure, Full length of Gudgeon Street) | Ponsonby | Night Shift Only | 12/05/2024 | 14/05/2024 |
Road Maintenance | Hargreaves Street (full road closure, Full length of Hargreaves Street) | Ponsonby | Night Shift Only | 12/05/2024 | 14/05/2024 |
Road Maintenance | College Hill (full road closure, Ponsonby Road to Beaumont Street) | Ponsonby/Freemans Bay | Night Shift Only | 14/05/2024 | 17/05/2024 |
Road Maintenance | England Street (full road closure, College Hill to Costley Street) | Ponsonby/Freemans Bay | Night Shift Only | 14/05/2024 | 17/05/2024 |
Road Maintenance | New Street (full road closure, College Hill to Dublin Street) | Ponsonby/Freemans Bay | Night Shift Only | 14/05/2024 | 17/05/2024 |
Road Maintenance | Wood Street (full road closure, College Hill to Georgina Street) | Ponsonby/Freemans Bay | Night Shift Only | 14/05/2024 | 17/05/2024 |
Slip Repair | Ahuroa Road (between J Tolhopf Road and Ahuroa Valley Road) | Puhoi | Stop/Go - 24 hours (traffic lights) | 29/04/2024 | 1/07/2024 |
Road Maintenance - Mill & Fill | Rakino Island (RP 24 to RP 2537) | Rakino Island | Day - Lane Closure - Stop/Go | 12/05/2024 | 12/05/2024 |
Bridge Repairs | Ramarama Road | Ramarama | Stop/Go - Try alternate route | 9/05/2024 | 13/05/2024 |
Crane Operation | Bell Road (full road closure, Masons Avenue to Herne Bay Road) | Remuera | Day Shift Only | 22/05/2024 | 22/05/2024 |
Road Maintenance | Benson Road (full road closure, Lucerne Road RAB to 104 Benson Road) | Remuera | Day Shift Only | 20/05/2024 | 20/05/2024 |
Road Maintenance | Combes Road (full road closure, 3 Combes Road to Victoria Avenue) | Remuera | Night Shift Only | 8/05/2024 | 13/05/2024 |
Road Maintenance | Glenbrook Street (full road closure, 3A Glenbrook Street to Victoria Avenue) | Remuera | Night Shift Only | 8/05/2024 | 13/05/2024 |
Stormwater Improvement | Grand View Road (full road closure, 23 Grand View Road to Peach Parade) | Remuera | Continuous Deployment | 20/05/2024 | 20/06/2024 |
Road Maintenance | Hiriri Avenue (full road closure, 3 Hiriri Avenue Road to Victoria Avenue) | Remuera | Night Shift Only | 8/05/2024 | 13/05/2024 |
Road Maintenance | Ingram Road (full road closure, 5 Ingram Road to Victoria Avenue) | Remuera | Night Shift Only | 8/05/2024 | 13/05/2024 |
Road Maintenance | Manawa Road (full road closure, 5 Manawa Road to Victoria Avenue) | Remuera | Night Shift Only | 13/05/2024 | 16/05/2024 |
Road Maintenance | Sonia Avenue (full road closure, 7 Sonia Avenue to Victoria Avenue) | Remuera | Night Shift Only | 13/05/2024 | 16/05/2024 |
Road Resurfacing - Asphalt Reseal | Victoria Avenue (AT-W172910 to Shore Road) | Remuera | Night - One Direction Detour - Stop/Go Control | 5/05/2024 | 16/05/2024 |
Road Maintenance | Victoria Avenue (full road closure, Aldred Road to Manawa Road) | Remuera | Night Shift Only | 8/05/2024 | 13/05/2024 |
Road Maintenance | Victoria Avenue (full road closure, Shore Road to Hiriri Road ) | Remuera | Night Shift Only | 13/05/2024 | 16/05/2024 |
Road Maintenance | Walton Street (full road closure, 7 Walton Street to Victoria Avenue) | Remuera | Night Shift Only | 8/05/2024 | 13/05/2024 |
Road Maintenance | Bush Road (full road closure, 80 Bush Road to Albany Expressway) | Rosedale | Night Shift Only | 19/05/2024 | 21/05/2024 |
Road Maintenance | Bushlands Park Drive (full road closure, 8 Bushlands Park Drive to Bush Road) | Rosedale | Night Shift Only | 19/05/2024 | 21/05/2024 |
Footpath Renewals | Piermark Drive | Rosedale | Contraflow | 13/05/2024 | 17/05/2024 |
Electrical Installation | Paunui Street (full road closure, Kaimata Street to Brookfield Street) | Saint Heliers | Day Shift Only | 24/05/2024 | 24/05/2024 |
Super Rugby Blues v Highlanders | Cricket Avenue (full road closure, Walters Road to Reimers Avenue) | Sandringham | Full road closured for the Super Rugby Blues v Highlanders from 5pm to 9.30pm | 18/05/2024 | 18/05/2024 |
Super Rugby Blues v Highlanders | Reimers Avenue (full road closure, Sandringham Road to Cricket Avenue) | Sandringham | Full road closured for the Super Rugby Blues v Highlanders from 5pm to 9.30pm | 18/05/2024 | 18/05/2024 |
Super Rugby Blues v Highlanders | Walters Road (full road closure, Sandringham Road to Kowhai Street) | Sandringham | Full road closured for the Super Rugby Blues v Highlanders from 5pm to 9.30pm | 18/05/2024 | 18/05/2024 |
Sealed Road Maintenance | Silverdale Street | Silverdale | Road Closure | 14/05/2024 | 16/05/2024 |
Construction Vehicle Access | Waterloo Road (full road closure, Emirali Road to Colin Chester Drive) | Silverdale | Continuous Deployment | 3/04/2023 | 13/05/2024 |
Asphalt Resurfacing | Mahurangi East Road (between James Street (Sandspit) and Arabella Lane) | Snells Beach | Stop/Go - Night Shift | 15/05/2024 | 16/05/2024 |
Road Reconstruction | Scott Road (full road closure, 64 Scott Road to Riverhaven Drive) | Stanmore Bay | Continuous Deployment | 4/12/2023 | 30/05/2024 |
Rehab | Walters Road | Takaanini | Night Lane closure. Stop/Go. Minor impact to traffic | 19/05/2024 | 20/04/2024 |
Level Crossing Improvement/Maintenance | Northcroft street (full road closure, Lake Road to Auburn Street) | Takapuna | Continuous Deployment | 15/04/2024 | 30/06/2024 |
GNC Traffic Limited | The Promenade Central (full road closure, Intersection of Hurstmere & The Promenade to Intersection of Killarney & The Promenade) | Takapuna | Full road closured for the GNC Traffic Limited from 7am to 1pm | 20/05/2024 | 23/05/2024 |
Slip Repair | Takatu Road (between Baddeleys Beach Road and End Of Road) | Tawharanui Peninsula | Stop/Go - 24 hours (traffic lights) | 29/04/2024 | 1/07/2024 |
Footpath, Kerb & Channel Renewal | Coronation Street (between State Highway 1 and Whakapirau Road) | Te Hana | One Way Detour / Footpath Closure / Stop/Go - Day Shift | 9/05/2024 | 17/05/2024 |
Footpath, Kerb & Channel Renewal | State Highway 1 (between Coronation Street (Te Hana) and Whakapirau Road) | Te Hana | Footpath Closure / Stop/Go - Day Shift | 14/05/2024 | 24/05/2024 |
AC Reseal | Camilla Grove | Totara Vale | Stop/ Go | 15/05/2024 | 15/05/2024 |
Road Maintenance - Mill & Fill | Cowes Bay Road (RP 5725 to RP 6225) | Waiheke Island | Day - Mobile Operation - Minor Impact | 16/05/2024 | 16/05/2024 |
Road Maintenance - Mill & Fill | Man O War Bay Road (South) (RP 1200 to RP 1700) | Waiheke Island | Day - Mobile Operation - Minor Impact | 17/05/2024 | 17/05/2024 |
Road Maintenance - Retaining Wall Repair | Wharf Road (RP 0443 to RP 0476) | Waiheke Island - Ostend | Day - Shoulder Closure - Minor Impact | 13/05/2024 | 13/05/2024 |
Preseal Repairs - Levelling | Palm Road (RP 0041 to RP 0684) | Waiheke Island - Palm Beach | Day - Lane Closure - Stop/Go | 16/05/2024 | 17/05/2024 |
Road Improvements | Quona Avenue (full road closure, Albrecht Avenue to Hillsborough Road) | Waikowhai | Continuous Deployment | 18/09/2023 | 30/06/2024 |
Slip Repair | Weranui Road (Rural between Hibiscus Coast Highway and Upper Waiwera Road) | Wainui | Stop/Go - 24 hours (traffic lights) | 13/05/2024 | 30/08/2024 |
Slip Repair | Moir Hill Road (between State Highway 1 and End Of Seal) | Warkworth | Stop/Go - 24 hours (traffic lights) | 1/05/2024 | 31/05/2024 |
Footpath, Kerb & Channel Renewal | Tomas Street (between State Highway 1 and End Of Road) | Wellsford | Footpath Closure / Stop/Go - Day Shift | 13/05/2024 | 24/05/2024 |
Stormwater Improvement | Wellpark Avenue (full road closure, Warnock Street to Old Mill Road) | Westmere/Grey Lynn | Continuous Deployment | 8/01/2024 | 7/07/2024 |
Repairs to Structure | Spedding Road (full road closure, Mamari Road to End of Speeding Road) | Whenuapai | Continuous Deployment | 29/02/2024 | 31/12/2024 |
Other roadworks and traffic updates
- Roadworks related to the 2023 flood and cyclone
- Latest traffic updates from NZ Transport Agency Waka Kotahi
- Events causing delays
Reasons for roadworks
AT operates a continuous programme of road maintenance and upgrades through our approved network of contractors. Other events, like filming, parades or car rallies can also cause temporary road closures.
Roadworks may also be carried out when services such as water, power, and telecommunications require maintenance or are part of larger infrastructure projects.
We aim to minimise any disruptions to your travel plans. However, temporary detours are sometimes necessary and delays may occur.
Your safety is important to us, so stay safe when you’re walking or driving in the area. Follow the signs and don’t get any closer than you must. Find out how roadworks may impact you.
Find out about our projects and roadworks.
Contact us
If you have any queries, contact us.